EV CHARGING

EV CHARGING

LEICESTER

Equipment: 14 high-powered EV chargers

Approx CO2 Saved Per Annum: 600T

Power Equivalent To: 1,400 electric coach miles

Fact 4

Overview

This project involved the design and installation of a fully integrated EV charging hub to support an electric coach fleet. We delivered 14 high-powered chargers alongside the supporting electrical infrastructure and civil engineering works.

Ashton After 2.JPG

The Challenge

Working alongside a steep, disused railway embankment presented significant engineering constraints. The retaining structures had to be carefully designed to maintain the stability of the existing bank during construction.

Our Solution

Our solution included the off-site manufacture of a containerised low-voltage switchroom, allowing civil works to progress concurrently. This reduced on-site activities and supported a more efficient installation programme.

IMG_2194.JPG

The Approach

We delivered the complete electrical design, civil engineering works and installation, coordinating all aspects of the project to provide an efficient and fully integrated charging infrastructure solution for the client.